Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 9 and Final between the City of Huntsville and Turner Construction Company for the New City Hall.
Resolution No.
body
Finance Information:
Account Number: 4015-14-00000-522010-00000000-
City Cost Amount: $1,213,814.90
Total Cost: $83,385,325.53
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 305 Fountain Circle
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☒ District 5 ☐
Additional Comments:
Change Order No. 9 and Final to include ASI 21 and RFI clean up; ASI 22-24, plus RFI cleanup, GCCR Extension, Miscellaneous RFIs; freezing weather delay (January 15-19); generator delay; two additional days for miscellaneous added scope after Certificate of Occupancy; parking garage water mitigation; Level 2 Mezzanine water mitigation; back charges for commissioning delays (add to Sain contract).