Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 3 and Final between the City of Huntsville and Fite Building Company for Construction Services for the New Public Safety Complex Phase 2.
Resolution No.
body
Finance Information:
Account Number: 4013-14-00000-522017-PHASE002
City Cost Amount: -$432,543.73
Total Cost: $18,183,784.60
Special Circumstances:
Grant Funded: NO
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address:
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☒
Additional Comments:
Change Order No. 3 and Final to include the following changes: Handrail at Bum Tower stoops; Add door sensors to four overhead doors in building E; Cap sprinkler line under stairs; Hang Racks in Building E; Relocate Canopies in K9 area; Deduct allowances and contingency.