Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 2 between the City of Huntsville and Fite Building Company for the Public Safety Training Facility Phase II.
Resolution No.
body
Finance Information:
Account Number: 4013-14-00000-522017-PHASE002
City Cost Amount: $986,428.46
Total Cost: $18,616,328.33
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 5635 Triana Boulevard
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☒ District 5 ☐
Additional Comments:
Change Order No. 2 to include the following: Furnish and install liner panels in the burn tower, grading, drainage, parking and landscape improvements (K9 Range), DOAS Mechanical System (additional 90 days), dog leg extension to running track, french drain for running track and additional cages for nitrogen cylinders