File #: 2023-1022   
Type: New Business for Consideration or Action Status: Passed
File created: 11/15/2023 In control: City Council Regular Meeting
On agenda: 1/11/2024 Final action: 1/11/2024
Title: Resolution authorizing the Mayor to enter into an Agreement between the City of Huntsville, Alabama and Garver, L.L.C., for Engineering Construction Administration Services for Martin Road Roadway Improvements, Phase II, Project No. 65-10-RD07 & ALDOT Project No. CRSAHV-STPAA-STPHV-4520(251). Resolution No.
Sponsors: Engineering
Attachments: 1. Garver Martin Road Roadway Improv Phase II complete.doc.pdf

Department:  Engineering

Subject:                                                                                                                                                Type of Action:   Approval/Action                 

title
Resolution authorizing the Mayor to enter into an Agreement between the City of Huntsville, Alabama and Garver, L.L.C., for Engineering Construction Administration Services for Martin Road Roadway Improvements, Phase II, Project No. 65-10-RD07 & ALDOT Project No. CRSAHV-STPAA-STPHV-4520(251).

 

Resolution No. 

 

 

 

 

 

 

body

Finance Information:

 

Account Number: TBD

City Cost Amount: up to $397,170.20

Total Cost: $1,985,851.00

 

Special Circumstances:

Grant Funded: N/A

Grant Title - CFDA or granting Agency: N/A

Resolution #: N/A

 

Location: (list below)

Address:  N/A

District:  District 1      District 2       District 3       District 4      District 5 

 

Additional Comments:  

A contract with Garver to provide construction engineering, inspection and administrative services for Martin Road Phase II between Old Jim Williams and Laracy Drive.  The project consists of approximately 1.5 miles of new 5-lane curb and gutter roadway.  Construction services will be in accordance with ALDOT construction inspection requirements to include surveying, testing and project management services during construction.  The cost is estimated at 10% of the construction cost and will be on a time and materials basis.