Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 1 and Final between the City of Huntsville and Pettus Plumbing & Piping, Inc. for Construction Services for the Art Museum HVAC Renovation.
Resolution No.
body
Finance Information:
Account Number: 3020-14-00000-523020-00000000
City Cost Amount: -$91,393.96
Total Cost: $3,401,926.04
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 300 Church Street
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☒
Additional Comments:
Change Order No. 1 and Final includes additional work to install the double doors on the roof; provide and installation of additional steel material for new doors in parapet wall; provide and installation of additional stucco to accommodate additional steel work; provide crane rental for hoisting steel to roof; 1 ton temporary mobile conditioning units at Pane E Vino; fuel tank with pump required; duct material to tie in temporary units; half estimated fuel costs and labor for fueling/power disruptions for Pane E Vino and Hsv Art Museum; tie in to existing backup generators; mechanically fasten 20 gauge metal over existing dens deck; and removal of 2” of height section of Stuck O & gypsum board; reinstall new dens deck prime; and clean all trash and debris.