Department: Engineering
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 2 to the Agreement between the City of Huntsville, Alabama and Wiregrass Construction Company, Inc., for Huntsville Northern Bypass COH Project No. 65-10-RD08 and ALDOT Project No. CRSA-STPHV-PE10(917).
Resolution No.
body
Finance Information:
Account Number: 3080-71-00000-524042-CONSTRUC-00172
City Cost Amount: $632,193.95
Total Cost: $35,327,792.24
Special Circumstances:
Grant Funded: N/A
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: N/A
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☐
Additional Comments:
Construction Supplemental Agreement #2 with Wiregrass Construction Company for Huntsville Northern Bypass COH Project No. 65-10-RD08 and ALDOT Project No. CRSA-STPHV-PE10(917).