Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 2 between the City of Huntsville and Arco Murray for Construction Services for the Huntsville Ice Complex Expansion.
Resolution No.
body
Finance Information:
Account Number: 4021-14-00000-522022-00000000
City Cost Amount: $721,140.97
Total Cost: $45,504,203.21
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 3185 Leeman Ferry Road
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☒ District 5 ☐
Additional Comments: Change Order No. 2 to include allowance reconciliation for undercut/backfill of unsuitable soils, concrete and electrical scopes for two sum pits, credit for overhead scoreboard in Competition Arena, allowance reconciliation for undercut/backfill as directed by Amiri Engineering, electrical changes to support revised projector screen, and lectern layout, changes per revised detail K1/A511 at high arched roof rake, expansion of Concession areas and addition of a Pizza Kitchen, Plumbing revision to replace the original trap primer system with trap guards. This Change order includes 16 additional calendar days for the Arena.