Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 2 and Final to the Fixed Price Agreement between the City of Huntsville, Alabama, and Consolidated Construction Company of Alabama for Legacy Park.
Resolution No.
body
Finance Information:
Account Number: 2500-14-00000-521014-00000000
City Cost Amount: $54,297.93
Total Cost: $ 4,735,925.93
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address:
District: District 1 ☒ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☐
Additional Comments:
Change Order No. 2 and Final includes - 1) Extend primary conduits to the new location per Huntsville Utilities 2) Changes to South Road as directed by the design team 3) Raise existing fire/water vault and grade to new elevation 4) Time extension (as directed by the design team) due to unsuitable soils 5) Misc. Changes 6) Storm drainage work and splash pads