Legislation Details

File #: 2026-718   
Type: New Business for Consideration or Action Status: Passed
File created: 6/24/2026 In control: City Council Regular Meeting
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Resolution authorizing the Mayor to enter into a Preliminary Engineering, Right-of-Way, Utility and Construction Agreement between the City of Huntsville and Alabama Department of Transportation for Slaughter Road at Madison Boulevard, Project No. 71-25-TI01 & ALDOT Project No. STPHV-4514(254), Supplemental Agreement #1. Resolution No.
Sponsors: Engineering
Attachments: 1. ALDOT Engineering,ROW,Utility & CA Agrmt Slaughter

Department:  Engineering

Subject:                                                                                                                                                Type of Action:   Approval/Action                 

title
Resolution authorizing the Mayor to enter into a Preliminary Engineering, Right-of-Way, Utility and Construction Agreement between the City of Huntsville and Alabama Department of Transportation for Slaughter Road at Madison Boulevard, Project No. 71-25-TI01 & ALDOT Project No. STPHV-4514(254), Supplemental Agreement #1.

 

Resolution No. 

 

 

 

 

 

 

body

Finance Information:

 

Account Number: 3080-71-00000-524000-ALDOT003-

City Cost Amount: $1,075,000.00

Total Cost: $ 5,375,000.00

 

Special Circumstances:

 

Grant Funded: N/A

Grant Title - CFDA or granting Agency: N/A

Resolution #: N/A

 

Location: (list below)

 

Address:  N/A

District:  District 1      District 2       District 3       District 4      District 5 

 

Additional Comments:  

Supplemental Funding Agreement No. 1 between the ALDOT and the City for Slaughter Road and Madison Boulevard Intersection Improvements to include an allocation of Federal Highway Infrastructure Program (HIP) funds.  Resulted in a decrease of MPO funding towards the project cost.