Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 4 and Final between the City of Huntsville and Chorba Contracting Corporation for the Construction Services of Martin Road Recreation Center.
Resolution No.
body
Finance Information:
Account Number: 4017-14-00000-522021-00000000
City Cost Amount: -$171,027.48
Total Cost: $7,550,933.59
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 150 Martin Road SW
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☒
Additional Comments:
Negative Change Order No. 4 and Final includes wall pads for north and south walls in both gyms; credits for unused allowances.