Skip to main content
Huntsville Logo

  Welcome to our new legislative management system! You can find meetings prior to January 2022 at our former site.

File #: 2026-84   
Type: New Business for Consideration or Action Status: Agenda Ready
File created: 1/6/2026 In control: City Council Regular Meeting
On agenda: 1/22/2026 Final action:
Title: Resolution authorizing the Mayor to execute Change Order No.3 and Final between the City of Huntsville and Pearce Construction Company, Inc. for the construction services of the HPD Crime Scene Investigation Building and Warehouse. Resolution No.
Sponsors: General Services
Attachments: 1. COMPLETE-CO3Final-Pearce-HPDCSIBldg.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No.3 and Final between the City of Huntsville and Pearce Construction Company, Inc. for the construction services of the HPD Crime Scene Investigation Building and Warehouse.

Resolution No.






body
Finance Information:

Account Number: 4017-14-00000-522019-00000000
City Cost Amount: -$106,251.39
Total Cost: $9,702,558.30
Special Circumstances:

Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A

Location: (list below)

Address: 815 Wheeler Avenue
District: District 1 ? District 2 ? District 3 ? District 4 ? District 5 ?

Additional Comments:
Negative Change Order #3 and Final includes: Credit for BDA system; install bumpers in warehouse; shower valve; grab bars at showers; additional sidewalk concrete; install TV outlet with power in lobby and add V/D drops in storage 104; switching for chemical exhaust hood in fume exhaust; increase in material cost on CMR 9R1; install mini split at warehouse electrical E200 (Add 21 days); chain link fence and gate modifications; install sod on disturbed areas along the east property line; crane warning signs for fence gates; relocate camera on warehouse and add a keypad to north entry door (Add 30 days); Heratherm Protocol oven; artwork package for rooms; added electrical outlets to fume exhaust 113 (Add 5 days); provide monitoring of the pre-action fire protection control panels by the fire alarm system; cent tube for Heratherm Advanced Protocal Oven; additional cameras in warehouse and additional painting; change out flush valves to sloan regal (Add 21 days); install beach pebbles under drains in court yard; provide crane sign with different orientation on Fiber Street; provide ventless hood for fume exhaust; add 4 card readers to interior doors and revise camera in warehouse; credits for unu...

Click here for full text