Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 4 between the City of Huntsville and Fite Construction Company, LLC for Sandra Moon Phase 4.
Resolution No.
body
Finance Information:
Account Number: 4017-14-00000-523023-PHASE004
City Cost Amount: $622,207.39
Total Cost: $32,423,935.21
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 7901 Bailey Cove Road
District: District 1 ☐ District 2 ☐ District 3 ☒ District 4 ☐ District 5 ☐
Additional Comments:
Change Order No. 4 to include; Building Signage in various locations, addition of (7) motors to manual basketball goals; install roof handrail/safety upgrade at theater high roof ladder, additional furring, framing to walls based on KPS drawings, and additional AV.