File #: 2023-743   
Type: New Business for Consideration or Action Status: Passed
File created: 8/23/2023 In control: City Council Regular Meeting
On agenda: 9/28/2023 Final action: 9/28/2023
Title: Resolution authorizing the Mayor to execute Change Order No. 5 and Final to the Fixed Price Agreement between the City of Huntsville, Alabama and Lee Builders, Inc., for the Joe Davis Stadium Renovation. Resolution No.
Sponsors: General Services
Attachments: 1. Complete-CO5-Lee Builders-Joe Davis Stadium.pdf

Department:  General Services

Subject:                                                                                                                                                Type of Action:   Approval/Action                 

title
Resolution authorizing the Mayor to execute Change Order No. 5 and Final to the Fixed Price Agreement between the City of Huntsville, Alabama and Lee Builders, Inc., for the Joe Davis Stadium Renovation.

 

Resolution No. 

 

 

 

 

 

 

body

Finance Information:

 

Account Number: 3020-14-00000-523021-00000000-

City Cost Amount: $ 686,834.82

Total Cost: $ 29,902,086.82

Special Circumstances:

 

Grant Funded: No

Grant Title - CFDA or granting Agency: N/A

Resolution #: N/A

 

Location: (list below)

 

Address:  3125 Leeman Ferry Road

District:  District 1      District 2       District 3       District 4      District 5 

 

Additional Comments:   Change Order No. 5 to include: excavate and backfill settling in Area 1, 2, and 7, reinstall footings, CMU, plumbing, concrete cap, sidewalks, chain link fence, and grout fill voids under sidewalks), deduct for unused signs, add for replacement of existing damaged toilets, add for re-work plumbing at Beer Garden hand sink, add for additional contract time and general conditions, add for repair of existing lavatory push buttons, add for composite fencing at Area 3, add for owner requested countertops and guardrails, add for owner-requested additional bleachers and seating, add for air-curtain switches, add for HOA switches, add for owner-requested Gate 2 video display boards, add for permanent light fixtures at terraces, add for replacing sprayers at lavatories, add for PRV valve, add for camera infrastructure at visitor side, add for owner-requested drinking fountains, add for irrigation controller, add for NEMA enclosures at camera platforms, add for additional contract time and general conditions, add for additional sign labor at Gate 2, and add for required ground-fault testing, add for relocated service packs, add for installation of Gate 2 LED monitors, add for photocells at flagpoles.