File #: 2023-035   
Type: New Business for Consideration or Action Status: Passed
File created: 2/24/2023 In control: City Council Regular Meeting
On agenda: 3/9/2023 Final action: 3/9/2023
Title: Resolution authorizing the Mayor to execute Change Order No. 4 to the agreement between the City of Huntsville and Turner Construction Company for the construction services for the New City Hall. Type of Document: Resolution No.
Sponsors: General Services
Attachments: 1. Complete-TurnerCO4-CityHall.pdf

Department:  General Services

Subject:                                                                                                                                                Type of Action:   Approval/Action                 

title
Resolution authorizing the Mayor to execute Change Order No. 4 to the agreement between the City of Huntsville and Turner Construction Company for the construction services for the New City Hall.

 

Type of Document: Resolution No. 

 

 

 

 

 

 

body

Finance Information:

 

Account Number: 4015-14-00000-522010-00000000

City Cost Amount: $260,578.27

Total Cost: $79,893,324.55

Special Circumstances:

 

Grant Funded: No

Grant Title - CFDA or granting Agency: N/A

Resolution #: N/A

 

Location: (list below)

 

Address: N/A

District:  District 1      District 2       District 3       District 4      District 5 

 

Additional Comments:  

 

Additional scope associated with response to ASI 8 Revision 1; changing toilet paper holders to OFCI, adding three paper towel dispensers; additional scope associated with RFI 159; additional scope associated with RFI 166; additional scope associated with response to ASI 9; returned shop drawing submittal for the Kitsap wall and planters; additional scope associated with response to additional water line installation; supply and install 12V batteries for door hardware power supplies; additional scope associated with the Fountain Circle tunnel wall; additional scope associated with response to ASI 10