Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 4 to the agreement between the City of Huntsville and Turner Construction Company for the construction services for the New City Hall.
Type of Document: Resolution No.
body
Finance Information:
Account Number: 4015-14-00000-522010-00000000
City Cost Amount: $260,578.27
Total Cost: $79,893,324.55
Special Circumstances:
Grant Funded: No
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: N/A
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☒ District 5 ☐
Additional Comments:
Additional scope associated with response to ASI 8 Revision 1; changing toilet paper holders to OFCI, adding three paper towel dispensers; additional scope associated with RFI 159; additional scope associated with RFI 166; additional scope associated with response to ASI 9; returned shop drawing submittal for the Kitsap wall and planters; additional scope associated with response to additional water line installation; supply and install 12V batteries for door hardware power supplies; additional scope associated with the Fountain Circle tunnel wall; additional scope associated with response to ASI 10