Department: Water Pollution Control
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 2 and Final to the Contract between the City of Huntsville, Alabama and Mark Johnson Construction, LLC, for Western Area WWTP Phase I Expansion, Project No. 71-22-SF01.
Resolution No.
body
Finance Information:
Account Number: 6050-76-00000-526000-00000000
City Cost Amount: Reduction in cost of $1,372.377.62
Total Cost: Amended Contract Amount $35,551,665.38
Special Circumstances:
Grant Funded: N/A
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: N/A
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☐
Additional Comments: Change order is needed to facilitate the scope of the project due to equipment and construction material delays and amend the final contract amount to $35,551,665.38 for a decrease of $1,372,377.62.