Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 2 to the Contract between the City of Huntsville and Pearce Construction Company, Inc., for the HPD Crime Scene Investigation Building and Warehouse.
Resolution No.
body
Finance Information:
Account Number: 4017-14-00000-522019-00000000
City Cost Amount: $78,398.77
Total Cost: $9,808,809.69
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 815 Wheeler Avenue
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☒ District 5 ☐
Additional Comments:
Change Order No. 2 to include the following changes; Provide mixing valves at 3 hose reels, Provide 110 volt, 20 amp circuit to feed chem exhaust hood, Install chain link fence in Vehicle Storage, Provide and install warehouse shelving racks and equipment, including hardware. Change order to include time extension of 14 days to Contract.