Department: General Services
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 1 to the agreement between the City of Huntsville and Miller and Miller, Inc. for construction services for the VBC East Parking Lot
Resolution No.
body
Finance Information:
Account Number: 3020-14-00000-521018-00000000
City Cost Amount: $123,911.46
Total Cost: $ 606,686.46
Special Circumstances:
Grant Funded: NO
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: West Side of Monroe Street
Address:
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☒ District 5 ☐
Additional Comments:
Change Order #1 to include removal and replacement of concrete pavement; additional site grading, storm sewer modifications; additional electrical, landscape and irrigation scope of work; additional engineering controls; additional inlet removal and modified inlet box, credit for scope reduction; additional concrete jointing pattern, standup curb; LED lighting install on existing parking lot poles