Department: Finance
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to execute Change Order No. 1 to the contract, awarded pursuant to Resolution No. 24-667, between the City of Huntsville and Stewart Electric Company, Inc for the Von Braun Center Lighting & Sprinkler Improvements project.
Resolution No.
body
Finance Information:
Account Number: 4020-00-00000-523049-00000000-
City Cost Amount: $ 119,942.15
Total Cost: $ 119,942.15
Special Circumstances:
Grant Funded: $ N/A
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 700 Monroe Street SW, Huntsville, Alabama 35801
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☐
Additional Comments:
Change Order No. 1 increases the contract price from $3,450,000.00 to $3,569,942.15