File #: 2024-1309   
Type: New Business for Consideration or Action Status: Passed
File created: 3/15/2024 In control: City Council Regular Meeting
On agenda: 3/28/2024 Final action: 3/28/2024
Title: Resolution authorizing the Mayor to execute Change Order No. 3 and Final to the Fixed Price Agreement between the City of Huntsville and Consolidated Construction Company for the Sandra Moon Phase 2. Resolution No.
Sponsors: General Services
Attachments: 1. Compelte-CO3-CCC-SandraMoonPh2.pdf

Department:  General Services

Subject:                                                                                                                                                Type of Action:   Approval/Action                 

title
Resolution authorizing the Mayor to execute Change Order No. 3 and Final to the Fixed Price Agreement between the City of Huntsville and Consolidated Construction Company for the Sandra Moon Phase 2.

 

Resolution No. 

 

 

 

 

 

 

body

Finance Information:

 

Account Number: 4013-14-00000-523023-PHASE002

City Cost Amount: $-153,700.42

Total Cost: $ 4,295,172.33

Special Circumstances:

 

Grant Funded: NO

Grant Title - CFDA or granting Agency: N/A

Resolution #: N/A

 

Location: (list below)

 

Address:  7901 Bailey Cove Road

District:  District 1      District 2       District 3       District 4      District 5 

 

Additional Comments:  

Change Order No. 3 and Final includes change to lighting requested per RFI’s, price to install wooden temporary ADA ramp, price to install engineered infill, change out one 150 amp main breaker, 150 amp breaker (deduct from project allowance 7 for electrical), BRE will run pipe (Deduct from allowance 7), remove and replace fire hydrant and valve location by auditorium, add 2 egress lights outside (allowance 7 and 4), changes to meet requirements from fire marshal