Department: Engineering
Subject: Type of Action: Approval/Action
title
Resolution authorizing the Mayor to enter into an Agreement between the City of Huntsville, Alabama and Johnson & Associates, Inc., for Engineering Hydraulic and Hydrologic Modeling Services for Flood Study for Fagan Creek, Project No. 71-25-DR01.
Resolution No.
body
Finance Information:
Account Number: 3080-71-00000-527000-00000000-
City Cost Amount: $67,215.00
Total Cost: $67,215.00
Special Circumstances:
Grant Funded: N/A
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: N/A
District: District 1 ☐ District 2 ☐ District 3 ☐ District 4 ☐ District 5 ☐
Additional Comments:
Contract between the City and Johnson and Associates for a flood study along Fagan Creek between Townsend Avenue and Adams Street adjacent to Huntsville Junior High School. Scope consists of flood modeling to determine options to minimize the floodplain on adjacent property.