Resolution authorizing the Mayor to execute Change Order No. 2 between the City of Huntsville and Consolidated Construction Company for the Sandra Moon Community Center Phase 2.
Resolution No.
body
Finance Information:
Account Number: 4013-14-00000-523023-PHASE002
City Cost Amount: $ 64,034.95
Total Cost: $ 4,448,872.75
Special Circumstances:
Grant Funded: NONE
Grant Title - CFDA or granting Agency: N/A
Resolution #: N/A
Location: (list below)
Address: 7901 Bailey Cove Road
District: District 1 ☐ District 2 ☐ District 3 ☒ District 4 ☐ District 5 ☐
Additional Comments:
Change Order No. 2 to include the removal of head block in theater; Additional hardware, doors and frames to meet ADA; changing color of door hardware; change keying system to Medeco and demolishing door frames 114B and R130C.