File #: 2024-1445   
Type: New Business for Consideration or Action Status: Passed
File created: 4/25/2024 In control: City Council Regular Meeting
On agenda: 5/9/2024 Final action: 5/9/2024
Title: Resolution authorizing the Mayor to execute Change Order No. 2 and Final to the Fixed Price Agreement between the City of Huntsville and Lambert Contracting LLC for the Sandra Moon Complex Phase 3. Resolution No.
Sponsors: General Services
Attachments: 1. Lambert - Sandra Moon - Phase 3 - Complete

Department:  General Services

Subject:                                                                                                                                                Type of Action:   Approval/Action                 

title
Resolution authorizing the Mayor to execute Change Order No. 2 and Final to the Fixed Price Agreement between the City of Huntsville and Lambert Contracting LLC for the Sandra Moon Complex Phase 3.

 

Resolution No. 

 

 

 

 

 

 

body

Finance Information:

 

Account Number: 4013-14-00000-523023-PHASE003

City Cost Amount: $213,106.73

Total Cost: $3,633,723.65

Special Circumstances:

 

Grant Funded: NONE

Grant Title - CFDA or granting Agency: N/A                     

Resolution #: N/A

 

Location: (list below)

 

Address:  7901 Bailey Cove Road

District:  District 1      District 2       District 3       District 4      District 5 

 

Additional Comments:  

Change Order No. 2 and Final to include emergency water line repair; addition of 900 of of 2”PVC water main; undercut east side parking along football field; fees for 2” irrigation meters; change asphalt paving building up; change thickness to base stone from 6 inches to 5 inches; replace and lower 3” water main at tennis courts; undercut at NW and south parking lot; playground changes- add 2 trash receptacles and remove 4 trees; tie to existing street light to new circuit at NW side; delete 29lf of 15” RCP and 1 inlet; undercut at SW corner of parking lot; fence modifications; extend sidewalk at HC parking; handicap ramp at gem and mineral building; north intersection- rework dith with riprap; French drain in south parking lot; add 17 wheel stops; allowance reconciliation/closeout of allowances