File #: 2023-890   
Type: New Business for Consideration or Action Status: Passed
File created: 10/23/2023 In control: City Council Regular Meeting
On agenda: 11/2/2023 Final action: 11/2/2023
Title: Resolution authorizing the Mayor to execute Change Order No. 1 between the City of Huntsville, Alabama and Mark Johnson Construction, LLC, for Western Area WWTP Phase I Expansion, Project No. 71-22-SF01. Resolution No.
Sponsors: Water Pollution
Attachments: 1. Mark Johnson Construction COMPLETE.pdf

Department:  Water Pollution Control

Subject:                                                                                                                                                Type of Action:   Approval/Action                 

title
Resolution authorizing the Mayor to execute Change Order No. 1 between the City of Huntsville, Alabama and Mark Johnson Construction, LLC, for Western Area WWTP Phase I Expansion, Project No. 71-22-SF01.

 

Resolution No. 

 

 

 

 

 

 

body

Finance Information:

 

Account Number: NA. No City Funds Involved.

City Cost Amount: NA. Time Extension Only. No additional City Funds Involved.

Total Cost: $ 36,924,043.00 original contract amount

Special Circumstances:

 

Grant Funded: NA

Grant Title - CFDA or granting Agency: NA

Resolution #: 22-546

 

Location: (list below)

 

Address:  NA

District:  District 1      District 2       District 3       District 4      District 5 

 

Additional Comments:   Change Order is needed to facilitate the scope of the project due to equipment and construction material delays. Time Extension change order only.  Account No.  N/A. No Additional City Funds Involved.